Norbar Case Study

CS-20 Coal Mine: Rio Tinto – Technofast Case Study

E

Site

Rio Tinto – Hunter Valley

E

Original Set-Up

Heavy steel TEE Bars and jacks need to be lifted and installed to tension the ropes and then removed.

E

Issues Experienced

  • Manual Handling Concerns
  • Rating concerns with 1” UNC bolts used with jacks
  • OH&S concerns due to working at heights
E

Installation Time

Old Method = 2 hours 30 minutes (2-3 personnel) per rope
New Method = 45 minutes(2 personnel) per rope

Time Saving = 1 hours 45 minutes

E

Application

Intermediate Boom Rope Support Tensioners

E

Technofast Product Used

EziTite IBS Tensioners — EZI-IBS-212X4-000.

E

Benefits Experienced

  • Easy installation and handling
  • Removed major OH&S concerns
  • Ability to check rope loads quickly and easily
E

Feedback Recieved

“Has received great acceptance from the on-site maintenance crew.”
– Hunter Valley User

Application Pictures

IBS Rope being tensioned with EziTite IBS EziTite hydraulic Nuts

IBS Rope being tensioned with EziTite® IBS EziTite Hydraulic Nuts.