Norbar Case Study
EBT 7000 Removes Resistant Marine Fender Bolts in One Shift
The Application
A major marine operator in North Queensland is undertaking an ongoing program to replace approximately 36 berthing fenders as required.
The fender cells have an expected service life of around 20 years and remain continuously exposed to saltwater and demanding marine conditions. Their size and location over the water create significant access and maintenance challenges.
Each cell is approximately 2.5 metres long, with a mounting flange approaching 3 metres in diameter. Replacing the fenders requires maintenance crews to access and release large fasteners positioned around the assembly.
During one replacement task, the team removed the more accessible bolts using its existing equipment. However, 10 remaining bolts resisted the impact wrenches being used.
The Challenge
When the impact wrenches could not release the remaining fasteners, the team’s fallback method involved flogging spanners.
This presented several operational and safety concerns:
Repeated manual striking and greater physical effort
Restricted access around the bolted connection
Extended exposure within the fender work area
Work windows affected by tides, wind and weather
The possibility of the task extending across several shifts
The site’s minimum three-person crew was required regardless of the removal method. The objective was therefore to provide the existing crew with a more controlled approach and reduce the time spent completing the bolt removal.
The project engineer approached Norbar after seeing the EvoTorque Battery Tool used successfully on other large industrial applications.
The Solution
Norbar supplied an EBT-119-7000 for an on-site trial.
The battery-powered tool provided a portable high-torque solution that could be positioned within the restricted work area. The socket was fully engaged with the fastener, while the reaction arm was positioned against a suitable support point to absorb the tool’s reaction force.
With the impact wrenches unable to make further progress, the EBT 7000 was operated at its maximum setting of 7,000 N·m.
The tool successfully released all 10 remaining bolts.
Project Benefits
Complete Bolt Removal
The EBT 7000 released all 10 remaining bolts after the impact wrenches reached their limit.
Completed in One Shift
The maintenance team completed the remaining bolt removal within a single shift.
No Flogging Spanners Required
The 10 remaining bolts were removed without reverting to manual flogging spanners.
Results
The EBT 7000 allowed the maintenance team to complete the remaining bolt removal within a single shift.
Under the previous approach, using flogging spanners could cause the work to extend across several shifts. Each additional shift required the crew to re-enter the work area and remain subject to changing tide, wind and weather conditions.
The EBT did not change the site’s minimum three-person crew requirement. Its value came from changing the removal method, eliminating flogging spanners for the 10 remaining bolts and reducing the number of separate work periods required.
Following the successful trial, the operator is considering incorporating the EBT 7000 into its annual maintenance procedure and wider fender replacement program.
Conclusion
The trial demonstrated how high-torque battery tooling can support difficult fastener removal on large marine infrastructure.
At its maximum 7,000 N·m setting, the EBT 7000 released bolts that the existing impact wrenches could not remove. The three-person crew completed the remaining bolt removal in one shift without using flogging spanners.
With approximately 36 fenders identified for replacement, the EBT 7000 gives the operator a more controlled and efficient option to consider for future maintenance.

Pictured: Berthing fender installation at a North Queensland wharf, where restricted access and marine exposure created a challenging bolt-removal application.

Pictured: Marine fender cell and chain assembly at the North Queensland wharf. Its size, position over the water and ongoing marine exposure complicated access to the mounting bolts.

Pictured: Norbar EBT-119-7000 engaged on a fender cell bolt, with the reaction arm positioned against a support point within the restricted work area.

Pictured: Wider view of the EBT-119-7000 during the on-site trial, showing the confined access and supported reaction arrangement used to remove the remaining bolts.
Facing a Difficult Marine Bolting Application?
Norbar can help assess your torque requirement, access limitations, socket arrangement and reaction point to identify a solution suited to the application.