Norbar Case Study
CS-25 Oil & Gas: Origin – Technofast Case Study
Site
Origin – Darling Downs Metering Station
Original Set-Up
One cassette style torque wrench
Issues Experienced
- Very time consuming
- OH&S concerns with pinch points
- Difficult to use
Installation Time
Old Method = 3-4 hours (2 personnel)
New Method = 1 hour (2 personnel)
Time Saving = 2 hours
Application
Tensioning of Standard pipe flanges
Technofast Product Used
EziTite® Hydraulic Bolts
Benefits Experienced
- Easy installation and handling
- Can be operated with the need for operator to be in the area
- Minimal physical excursion required
Feedback Recieved
“I was very impressed at the speed in which the entire flange was tensioned and the accuracy, we had difficulty achieving this much accuracy in the past with the old method.” – Site Supervisor
Application Pictures

EziJac Bolt Tensioner installed on 50% of flange studs ready for pressurisation.